Brulez Trenching LLC is currently working on Contract D, from Silver Moon Resort to Hunter and Daring Thruway Road. Contract D includes approximately 63 collections. The crew expects to remain in this area for 60 to 75 days before moving to Crestline Road. A second crew is completing cleanup from Saddle Road to Idyll Acres. The Idyll Acres lift station surge tank was installed last week, and the wet well is still being fabricated by Allen Plastics in Sedalia. Allen Plastics indicated that the wet well is expected to ship during the first week of October. During the past month, 12 connections were completed, bringing the total completed connections to approximately 222. All the connections and mains are now completed for the Saddle Road project. Tony will continue maintaining a punch list as customers request tough-up items. Based on the updated schedule, the project may be completed by April 2027.